This week Turner Construction will host a Sub-Tier Outreach Event between the primes and second and third their subcontractors immediately following the job walk in an effort to build relationships and to help prime subcontractors reach their LBE/SLBE goals.

Each job walk is scheduled to start at 1pm. The job walk meeting point will be at the “Meet and Greet” area inside Terminal 1 right next to the TSA security checkpoint. Proceed inside the terminal towards the security line as if you were boarding a flight. The “Meet and Greet” area is directly to the right of the security checkpoint inside Terminal 1.

For TSA security purposes, please provide Turner with the full legal name, Date of Birth and Company Name of each job-walk attendee 24 hours prior to your scheduled job walk time. Attendee’s must bring a valid/current form of Identification with them during the job walk as well. This information should be sent to Brendan Crockett, bcrockett@tcco.com.

The Sub-tier Outreach event will be held immediately after the job walk in Turner’s Site Office at 2:30 PM. Our office is located in the Oakland Airport Maintenance Building, 1100 Airport Drive, Second Floor located in the green area on the map below and has the logo on the side of the building.

If you are interested in bidding on the M102 Renovation Project, we strongly recommend subcontractors attend both the job walk and the Sub-tier Outreach event in an effort to help with bidding requirements and scope for this project. Please check the dates of each pre-bid job walk carefully as to what trades will be highlighted. A reminder that this is the first phase of bidding and two subsequent bid packages are forthcoming.

Job Walk Schedule:

(Please note the Demolition Job walk has been moved to Wednesday Feb. 27th)

- Site Demo/Paving/Concrete, Glazing, Micropiles and Structural Concrete –
   Tues. Feb 26th @ 1pm.

- Structural Steel and Misc. Iron, Demolition - Wed. Feb. 27th @ 1pm.

- All MEPF, Low Voltage, and Elevator Trades– Thurs. Feb. 28th @ 1pm.

Please contact Brendan Crockett (bcrockett@tcco.com) with any questions.

 


 

 